Amur GPP construction is 87% complete in early October 2022

Restoration and pre-commissioning are underway on the licensed units of the Amur GPP process line 1 and 2. Installation of process pipelines on the gas fractionation unit and the natural gas liquid purification unit of process line 1 has been completed; testing of these process pipelines for strength, blowdown, re-assembly and handover for pre-commissioning are underway. Application of insulation onto process pipelines and equipment on the helium fine purification, liquefaction and filling unit of process line 3 is nearing completion. Core scope of construction and installation works on the unit for dehydration and removal of impurities has been completed; pre-commissioning is underway. Pre-commissioning is underway on process line 4: loop testing and re-assembly of static equipment are underway; hot running-in of the air cooler motors has been completed. Welding has been completed, re-assembly and blowdown of the process pipelines and laying of cable lines are underway. Installation and oil flus