Amur GPP construction is 87% complete in early October 2022
Restoration and pre-commissioning are underway on the licensed units of the Amur GPP process line 1 and 2.
Installation of process pipelines on the gas fractionation unit and the natural gas liquid purification unit of process line 1 has been completed; testing of these process pipelines for strength, blowdown, re-assembly and handover for pre-commissioning are underway.
Application of insulation onto process pipelines and equipment on the helium fine purification, liquefaction and filling unit of process line 3 is nearing completion. Core scope of construction and installation works on the unit for dehydration and removal of impurities has been completed; pre-commissioning is underway.
Pre-commissioning is underway on process line 4: loop testing and re-assembly of static equipment are underway; hot running-in of the air cooler motors has been completed. Welding has been completed, re-assembly and blowdown of the process pipelines and laying of cable lines are underway. Installation and oil flus
1 view
112
29
2 years ago 00:04:10 1
Amur GPP construction is 87% complete in early October 2022
2 years ago 00:02:40 4
Амурский ГПЗ. О мировом лидерстве, ценных компонентах газа и «небоскребах» на Амуре
3 years ago 00:13:23 1
«Газпром» день за днем – 2021
4 years ago 00:05:33 1
Construction Progress at Amur GPP in July 2020 Achieves 64.2%